China Shenhua Energy (01088): Beihai Second Phase Unit 4 passes 168-hour trial operation.

date
20:32 28/12/2025
avatar
GMT Eight
China Shenhua (01088) announced that in recent days, its controlling subsidiary Guangdong Guoneng Beihai Power Generation Co., Ltd. ("Beihai Power") successfully completed the 168-hour trial operation of Unit 4 of the Beihai Phase II expansion project ("Beihai Phase II") and handed it over for commercial operation. With this, both of the 1,000 MW ultra-supercritical once-through reheat coal-fired generating units at the Beihai Phase II project are now fully operational.
China Shenhua Energy (01088) announced that recently, its controlling subsidiary Guoneng Guangtou Beihai Power Generation Co., Ltd. ("Beihai Power") with a stake of approximately 52% successfully passed the 168-hour trial operation of Unit 4 in the Beihai Power Phase II expansion project ("Beihai Phase II"), and has been transferred to commercial operation. With this, both 1000MW ultra-supercritical once-through reheat coal-fired power generation units in Beihai Phase II are now fully operational. During the trial operation period, the units operated smoothly with excellent environmental performance, as the emissions of particulate matter, sulfur dioxide, and nitrogen oxides were much lower than the ultra-low emission standards, meeting the emission standards for gas-fired power generation units. After the operation of Beihai Phase II, Beihai Power has become the largest supportive and regulating power source in the region, providing strong support for the security and stability of the regional power grid and the construction of new power systems.