The assembly of the No. 7 unit at the Tianwan Nuclear Power Plant has been completed, and it has entered the phase of core testing.
On August 18, with the completion of the core loading correctness verification and the beginning of the protective tube component reinstallation, the first nuclear fuel loading work for Unit 7 of the Tianwan Nuclear Power Plant in Lianyungang, Jiangsu, was successfully concluded, entering the nuclear commissioning phase, laying a solid foundation for the subsequent criticality, grid connection, and commercial operation of the reactor.