Sinoma Energy Conservation has signed a long-term operation and maintenance service and spare parts supply contract for the Ghana Gas Turbine Waste Heat Power Plant.

date
05/04/2026
Recently, CNBM Energy Conservation signed a long-term operation and maintenance service contract and spare parts supply contract with GENSER ENERGY COTE D'IVOIRE SA for the Ghana GECS 522MW waste heat power plant. According to the contract, CNBM Energy Conservation will provide production operation and maintenance services as well as spare parts supply for four 522MW gas engine waste heat power plants located in the northwestern part of Ghana for a period of ten years. These power plants were all constructed by CNBM Energy Conservation under the engineering, procurement, and construction (EPC) mode.