New Energy: Two new coal power projects pass 168-hour trial operation.

date
30/03/2026
Sina Finance reported on March 30th that Xinji Energy announced that the 21000MW ultra-supercritical supercritical reheat coal-fired power generation project newly built by its controlling subsidiary Shangrao Xintou Power Generation Co., Ltd. is located in Guangxin District, Shangrao City, Jiangxi Province. The two units completed 168 hours of full-load trial operation on December 30, 2025, and March 25, 2026, respectively, and entered into commercial operation. The 2660MW ultra-supercritical supercritical reheat coal-fired power generation project newly built by its controlling subsidiary Zhongmei Xinji Power Generation Co., Ltd. is located in Fengyang County, Chuzhou City, Anhui Province. The two units completed 168 hours of full-load trial operation on January 30, 2026, and March 27, 2026, respectively, and entered into commercial operation.