Zhongyan Dadi: Signed a 77,000,300 RMB subcontracting contract with CNNC II

date
14/11/2025
Zhongyan Dadi announced that it recently signed a subcontracting contract for the land drainage project GE tunnel excavation part and CC well foundation project of Units 1 and 2 of Zhejiang Jinqiemen Nuclear Power Plant with China Nuclear Industry Second 22 Construction Co., Ltd. The total contract price, including tax, is tentatively set at 77,000,300 yuan, with a duration of 140 days. This contract falls within the company's main business scope, and if successfully completed, it will provide business support for the company's continued development, with an expected positive impact on future performance. However, project execution may be affected by factors such as weather, which poses certain risks.